2018 Report on James Webb Space Telescope (JWST): Integration and Test Challenges Have Delayed Launch and Threaten to Push Costs Over Cap

Nonfiction, Science & Nature, Science, Physics, Astronomy, Astrophysics & Space Science
Cover of the book 2018 Report on James Webb Space Telescope (JWST): Integration and Test Challenges Have Delayed Launch and Threaten to Push Costs Over Cap by Progressive Management, Progressive Management
View on Amazon View on AbeBooks View on Kobo View on B.Depository View on eBay View on Walmart
Author: Progressive Management ISBN: 9781370563555
Publisher: Progressive Management Publication: March 1, 2018
Imprint: Smashwords Edition Language: English
Author: Progressive Management
ISBN: 9781370563555
Publisher: Progressive Management
Publication: March 1, 2018
Imprint: Smashwords Edition
Language: English

JWST, a large, deployable telescope intended to be the successor to the Hubble Space Telescope, is one of NASA's most complex and expensive projects, at an anticipated cost of $8.8 billion. Congress set an $8 billion JWST development cost cap in 2011, and the remaining $837 million is for its operations costs. JWST is intended to revolutionize our understanding of star and planet formation and advance the search for the origins of our universe. With significant integration and testing planned for the remaining period until launch, the JWST project will still need to address many challenges during the remainder of integration and testing.

In 2017, the National Aeronautics and Space Administration's (NASA) James Webb Space Telescope (JWST) project delayed its launch readiness date by at least 5 months, and further delays are likely. The delay—from October 2018 to a launch window between March and June 2019—was primarily caused by components of JWST's spacecraft taking longer to integrate than planned. JWST made considerable progress toward the completion of integration and test activities in the past year. However, the project used all remaining schedule reserve—or extra time set aside in the schedule in the event of delays or unforeseen risks—to address technical issues, including an anomaly on the telescope found during vibration testing. Extending the launch window provided the project up to 4 months of schedule reserve. However, shortly after requesting the new launch window in September 2017, the project determined that several months of schedule reserve would be needed to address lessons learned from the initial folding and deployment of the observatory's sunshield (see image). Given remaining integration and test work ahead—the phase in development where problems are most likely to be found and schedules tend to slip—coupled with only 1.5 months of schedule reserves remaining to the end of the launch window, additional launch delays are likely. The project's Standing Review Board will conduct an independent review of JWST's schedule status in early 2018 to determine if the June 2019 launch window can be met.

View on Amazon View on AbeBooks View on Kobo View on B.Depository View on eBay View on Walmart

JWST, a large, deployable telescope intended to be the successor to the Hubble Space Telescope, is one of NASA's most complex and expensive projects, at an anticipated cost of $8.8 billion. Congress set an $8 billion JWST development cost cap in 2011, and the remaining $837 million is for its operations costs. JWST is intended to revolutionize our understanding of star and planet formation and advance the search for the origins of our universe. With significant integration and testing planned for the remaining period until launch, the JWST project will still need to address many challenges during the remainder of integration and testing.

In 2017, the National Aeronautics and Space Administration's (NASA) James Webb Space Telescope (JWST) project delayed its launch readiness date by at least 5 months, and further delays are likely. The delay—from October 2018 to a launch window between March and June 2019—was primarily caused by components of JWST's spacecraft taking longer to integrate than planned. JWST made considerable progress toward the completion of integration and test activities in the past year. However, the project used all remaining schedule reserve—or extra time set aside in the schedule in the event of delays or unforeseen risks—to address technical issues, including an anomaly on the telescope found during vibration testing. Extending the launch window provided the project up to 4 months of schedule reserve. However, shortly after requesting the new launch window in September 2017, the project determined that several months of schedule reserve would be needed to address lessons learned from the initial folding and deployment of the observatory's sunshield (see image). Given remaining integration and test work ahead—the phase in development where problems are most likely to be found and schedules tend to slip—coupled with only 1.5 months of schedule reserves remaining to the end of the launch window, additional launch delays are likely. The project's Standing Review Board will conduct an independent review of JWST's schedule status in early 2018 to determine if the June 2019 launch window can be met.

More books from Progressive Management

Cover of the book From Transformation to Combat: The First Stryker Brigade at War - The Test of Combat in Iraq in 2003 - 2004, Mosul, Baghdad, An Najaf, Tall Afar, Carter Ham by Progressive Management
Cover of the book Application of Advances in Telemedicine for Long-Duration Space Flight: Robotic Telepresence and Teletrauma Support, Body Sensors, Security, Field Testing on Mt. Everest, Video Consultations by Progressive Management
Cover of the book Essential History of the Shippingport Atomic Power Station: 1957 First Large-Scale Nuclear Power Plant in America, Work of Admiral Rickover, Pressurized Water Reactor, Historic American Engineering by Progressive Management
Cover of the book Chad in Perspective: Orientation Guide: Geography, History, Economy, Society, Security, Military, Religion, Saharan, Soudanian Regions, N'Djamena, Moundou, Sarh, Sara, Toubou and Daza by Progressive Management
Cover of the book Biodiesel Fuel Handling and Use Guidelines for Users, Blenders, Distributors: Quality Specifications, Benefits and Drawbacks, Issues and Questions, Definitions, MSDS by Progressive Management
Cover of the book ISIS: The Terrorist Group That Would Be a State - ISIL, Islamic State, Jihadist Strategy and Savagery, Strengths and Weaknesses, al-Zarqawi, al-Qaeda, al-Baghdadi, al-Nusra, Caliphate, al-Suri, Syria by Progressive Management
Cover of the book History's Role in Operational Design and Planning: How Germany's Failed Invasion Provides Insight into U.S. and Chinese Perspectives on Anti-Access Area Denial A2AD - China's Strategy and Capabilities by Progressive Management
Cover of the book Ukraine Encyclopedia: Comprehensive Coverage from History to the Current Crisis with Russia, Official Reports and Guides, Crimea, Military, Orange Revolution, Economy, Culture and People by Progressive Management
Cover of the book 21st Century Adult Cancer Sourcebook: Nonmelanoma Skin Cancer - Squamous Cell Carcinoma and Basal Cell Carcinoma (BCC and SCC) - Clinical Data for Patients, Families, and Physicians by Progressive Management
Cover of the book Lost Unconventional Warfare Lessons from the Yugoslav Front: World War II, Cetniks, Guerrilla Warfare, German Anti-Guerrilla Tactics and Doctrine, OSS Involvement, Plans for Demobilization by Progressive Management
Cover of the book Bosnia and Herzegovina in Perspective: Orientation Guide and Cultural Orientation: Geography, History, Economy, Society, Military, Religion, Serbs and Croats, Sarajevo, Tuzla, Zenica, Mostar by Progressive Management
Cover of the book The PLA at Home and Abroad: Assessing the Operational Capabilities of China's Military - Uyghurs, Spratly and Senkaku Islands, Tibet, Domestic Riots, Taiwan, Chinese-Russian Exercises by Progressive Management
Cover of the book FBI Report: A Guide to Conducting Research in FBI Records, the FBI History Program - Presidential Libraries, Library of Congress, Papers of the Attorneys General by Progressive Management
Cover of the book Battlefield of the Future: 21st Century Warfare Issues - Air Theory for the 21st Century, Cyberwar, Biological Weapons and Germ Warfare, New-Era Warfare by Progressive Management
Cover of the book Expanding Fixed-Wing Aircraft Capability in U.S. Army Aviation Operations - UH-60L Blackhawk, CH-47F Chinook, C-23B, C-27J, BCT, Intra-Theater Airlift, Joint Cargo Aircraft (JCA), Ground Force Support by Progressive Management
We use our own "cookies" and third party cookies to improve services and to see statistical information. By using this website, you agree to our Privacy Policy