Skylab Mission Report: Second Visit - 1973 Space Station Mission by Bean, Garriott, and Lousma, Mission Activities, Hardware, Anomalies, Science Experiments, Crew Health, EVAs

Nonfiction, Science & Nature, Technology, Aeronautics & Astronautics, Science, Physics, Astrophysics & Space Science
Cover of the book Skylab Mission Report: Second Visit - 1973 Space Station Mission by Bean, Garriott, and Lousma, Mission Activities, Hardware, Anomalies, Science Experiments, Crew Health, EVAs by Progressive Management, Progressive Management
View on Amazon View on AbeBooks View on Kobo View on B.Depository View on eBay View on Walmart
Author: Progressive Management ISBN: 9781476295763
Publisher: Progressive Management Publication: May 18, 2012
Imprint: Smashwords Edition Language: English
Author: Progressive Management
ISBN: 9781476295763
Publisher: Progressive Management
Publication: May 18, 2012
Imprint: Smashwords Edition
Language: English

This official NASA internal document - converted for accurate flowing-text ebook format reproduction - is a comprehensive evaluation of the operational and engineering aspects of the second manned visit to the Skylab space station and includes the performance of experiment hardware that is under Johnson Space Center management; the crew's evaluation of the visit; and other visit-related items of interest such as medical aspects and hardware anomalies.

The space vehicle, consisting of a modified Apollo command and service module payload on a Saturn IB launch vehicle, was inserted into a 231.3 by 154.7 kilometer orbit. Rendezvous maneuvers were performed during the first five orbits as planned. During the rendezvous, the command and service module reaction control system forward firing engine (quad B) oxidizer valve leaked. The quad was isolated. Stationkeeping with the Saturn Workshop began approximately 8 hours after lift-off with docking being performed about 30 minutes later.

The crewmen experienced motion sickness during the first three visit days. Consequently, the Saturn Workshop activation and experiment implementation activities were curtailed. By adjusting the crew's diet and maintaining a low work load, the crew was able to complete the adjustment to space flight in 5 days, after which the flight activities were returned to normal.

The first extravehicular activity was delayed to visit day 10 because of the crew's motion sickness. The extravehicular activity lasted almost 6.5 hours during which time the crew changed the Apollo Telescope Mount film, deployed the twin-pole sun shield, inspected and performed repair work on the S055 (Ultraviolet Spectrometer) experiment, deployed the S149 (Particle Collection) experiment, and installed the calibration shield from experiment S230 (Magnetospheric Particle Composition). A second extravehicular activity was performed on visit day 28 and lasted 4 hours and 30 minutes. A third extravehicular activity was accomplished on visit day 57 with a duration of 2 hours and 45 minutes to retrieve the expended film on the Apollo Telescope Mount solar experiments and experiments S230 and S149. Earth Resources Experiment Package activities included 39 passes with a total of 930 minutes of data. All experiment coverage was normal with the exception of the loss of experiment S193 (Microwave Radiometer/Scatterometer and Altimeter) when the antenna failed to operate during data pass 29. A series of medical experiments was accomplished which assessed the effect of a 59-day duration space mission on the crewmen. Included were a hematology and immunology program, a mineral balance assessment, an evaluation of the changes in hormonal and associated fluid and electrolyte parameters, the extent of bone mineral loss, the cardiovascular effects utilizing the lower body negative pressure experiment and the vectorcardiogram, and an assessment of the metabolic activity.

View on Amazon View on AbeBooks View on Kobo View on B.Depository View on eBay View on Walmart

This official NASA internal document - converted for accurate flowing-text ebook format reproduction - is a comprehensive evaluation of the operational and engineering aspects of the second manned visit to the Skylab space station and includes the performance of experiment hardware that is under Johnson Space Center management; the crew's evaluation of the visit; and other visit-related items of interest such as medical aspects and hardware anomalies.

The space vehicle, consisting of a modified Apollo command and service module payload on a Saturn IB launch vehicle, was inserted into a 231.3 by 154.7 kilometer orbit. Rendezvous maneuvers were performed during the first five orbits as planned. During the rendezvous, the command and service module reaction control system forward firing engine (quad B) oxidizer valve leaked. The quad was isolated. Stationkeeping with the Saturn Workshop began approximately 8 hours after lift-off with docking being performed about 30 minutes later.

The crewmen experienced motion sickness during the first three visit days. Consequently, the Saturn Workshop activation and experiment implementation activities were curtailed. By adjusting the crew's diet and maintaining a low work load, the crew was able to complete the adjustment to space flight in 5 days, after which the flight activities were returned to normal.

The first extravehicular activity was delayed to visit day 10 because of the crew's motion sickness. The extravehicular activity lasted almost 6.5 hours during which time the crew changed the Apollo Telescope Mount film, deployed the twin-pole sun shield, inspected and performed repair work on the S055 (Ultraviolet Spectrometer) experiment, deployed the S149 (Particle Collection) experiment, and installed the calibration shield from experiment S230 (Magnetospheric Particle Composition). A second extravehicular activity was performed on visit day 28 and lasted 4 hours and 30 minutes. A third extravehicular activity was accomplished on visit day 57 with a duration of 2 hours and 45 minutes to retrieve the expended film on the Apollo Telescope Mount solar experiments and experiments S230 and S149. Earth Resources Experiment Package activities included 39 passes with a total of 930 minutes of data. All experiment coverage was normal with the exception of the loss of experiment S193 (Microwave Radiometer/Scatterometer and Altimeter) when the antenna failed to operate during data pass 29. A series of medical experiments was accomplished which assessed the effect of a 59-day duration space mission on the crewmen. Included were a hematology and immunology program, a mineral balance assessment, an evaluation of the changes in hormonal and associated fluid and electrolyte parameters, the extent of bone mineral loss, the cardiovascular effects utilizing the lower body negative pressure experiment and the vectorcardiogram, and an assessment of the metabolic activity.

More books from Progressive Management

Cover of the book Building the Decision-Making Environment in the Information Age: An Analysis of Defense Program Manager Decision-Making in Complex and Chaotic Program Environments - Sensemaking and Nousmaking by Progressive Management
Cover of the book 2011 Complete Guide to Ivory Coast (Cote d'Ivoire): Civil War and Crisis, Laurent Gbagbo, New Force Rebels, Ouattara, Yamoussoukro, Abidjan, History, Government, Politics - Authoritative Coverage by Progressive Management
Cover of the book 21st Century U.S. Military Manuals: Afoot in the Desert, Desert Survival, Deserts of the World Marine Corps Field Manual - FMFRP 0-53 (Value-Added Professional Format Series) by Progressive Management
Cover of the book 21st Century U.S. Military Documents: Air Force General Flight Rules, Aircraft Cockpit and Formation Flight Signals by Progressive Management
Cover of the book Lessons from the Normandy Invasion of World War II: Staff Development, Deception Operations, and Force Projection - Complexity of Planning, Sluggish Progress, Signals Intelligence and SHAEF Staff by Progressive Management
Cover of the book People's Republic of China Anti-Satellite (ASAT) and Space Warfare Programs, Policies and Doctrines: An Assessment including the 2007 Shootdown Incident, Space Weapons by Progressive Management
Cover of the book 21st Century Phenylketonuria (PKU) Sourcebook: Clinical Data for Patients, Families, and Physicians - Folling's Disease, PAH Deficiency, Sapropterin, Kuvan, Screening, Diet, Medicine, Pregnancy by Progressive Management
Cover of the book Understanding Islam and Its Impact on Latin America and the Caribbean: Islamic Fundamentalism, Terrorist Attack Targets and Support, Today's Islamic Threat, Regional Engagement and Cooperation by Progressive Management
Cover of the book 21st Century Adult Cancer Sourcebook: Non-Small Cell Lung Cancer (NSCLC) - Clinical Data for Patients, Families, and Physicians by Progressive Management
Cover of the book Countering Weapons of Mass Destruction: A Preliminary Field Study in Improving Collaboration - WMD Counterproliferation and the Risk of Improvised Nuclear Devices (IND), Use of Additive Manufacturing by Progressive Management
Cover of the book Historical Analogs for the Stimulation of Space Commerce: Case Studies of the Transcontinental Railroad, Aerospace Industry, Telephone Industry, Scientific Research in Antarctica, Public Works by Progressive Management
Cover of the book Conflict Management and "Whole of Government": Useful Tools for U.S. National Security Strategy? Loose Nukes, WMD, Fukushima, Rinderpest, Embassy Security, Afghanistan, Iraq, Sudan by Progressive Management
Cover of the book Air National Guard Family Guide: History, Structure, Life, Managing Deployment, When Bad Things Happen, Post-Traumatic Stress Disorder by Progressive Management
Cover of the book On the Frontier: Preparing Leaders: Yesterday, Today, and Tomorrow: U.S. Army Command and General Staff College 125th Anniversary 1881-2006 - End of Détente, Prairie Warrior, Iraqi Freedom by Progressive Management
Cover of the book Mind-Sets and Missiles: A First Hand Account of the Cuban Missile Crisis - Detailed Chronology of Intelligence Failures and Successes, President Kennedy and the Soviet Missiles in Cuba by Progressive Management
We use our own "cookies" and third party cookies to improve services and to see statistical information. By using this website, you agree to our Privacy Policy